INSTALLATION GUIDE
DESIGN PROCESS
FREE IN-HOME CONSULTATION:
Discuss scope of work, define personal style, & measure space.
PROPOSAL & DESIGN PRESENTATION:
Create a design presentation with 3D renderings; Generate an estimate of both product and labor
DETERMINE:
Sign final proposal and contract to order materials; Determine the project schedule
DELIVER:
Schedule delivery of products; Communicate throughout project; Follow up to ensure 100% satisfaction
STEP
#1
STEP
#2
STEP
#3
STEP
#4
INSTALLATION PROCESS
1. Removal
2. Construct
3. Trades
4. Drywall
5. Cabinets
6. Floors
7. Top Template
8. Trim
9. Paint
10. Top Install
11. Tile
12. Completion
PRODUCT LEAD TIMES
CABINETRY:
Depending on the manufacturer; 2-8 weeks
COUNTERTOPS:
Laminate 5-10 days
Quartz & Granite 2-3 weeks
Solid 7-14 days
FLOORING:
All types 2-3 weeks
LIGHTING:
All types 2-3 weeks
PLUMBING:
1-3 weeks
HARDWARE:
1-2 weeks